Location : Supsa, Georgia
Client : GPC-Georgian Pipeline Company, Georgia
Project Description : The project was the construction of main civil works and buildings of Supsa Oil Terminal including control and administration building, maintenance workshop, substation, security gate house and fire station. Steel structures including shelters for export pumps, fire water pumps, diesel transfer pumps, runway beams, access platforms, support frames for cabling. Foundations including piling for pumps, generators, tankage, steel structures, pipe tracks and pipe supports. Roads, bund walls, site levelling and drainage works.
Completion Date : January, 1999